Public consultation: new EU guideline compliant approach for the coordination of assets for system operations and market procedures

Historically all the key tasks regarding system operations and market procedures for large Production Units were organised with the Access Responsible Party via the CIPU Contract (Coordination of Injection of Production Units). The implementation of operational information requirements and development of new roles as imposed by the European Guideline on Electricity Transmission System Operation, the further decentralisation of generation, development of demand side management and emergence of new types of market parties are requiring a change of this historical contract.

This proposal is the result of an analysis and extensive discussions with relevant stakeholders in the framework of the iCAROS project (integrated Coordination of Assets for Redispatching and Operational Security). To clarify the future context in which the procedures are to be organized, an introductory note provides a broader picture of the future roles and responsibilities as required by the European Guidelines. Besides two other design notes are consulted elaborating the design principles for the new procedures for respectively the Outage Planning Agent and the Scheduling Agent. Finally a fourth document describes how congestion risks will be considered for the delivery of balancing services.

Note that the scope of the design notes concerns the assets connected on the ELIA grid and to ELIA-connected CDS, regardless of whether the asset is directly connected to the ELIA grid or locally on the site of a demand facility or CDS. The inclusion of assets connected to DSO grids is subjects to a separate trajectory between ELIA and Synergrid and will be communicated at a later time.

The key objective of this consultation is to receive input from stakeholders regarding the design principles and the adaptations which need to be foreseen in the new Federal Grid Code. In a next stage Elia will further refine the design and develop an implementation trajectory in close collaboration with the different stakeholders.

Stakeholders are asked to provide their remarks, concerns, and suggestions on the proposed design via the online form on the ELIA website. The consultation is open from 11 December 2017 until 15 January 2018 included (18h00).

Set of design notes:

  • Future roles and responsibilities for the delivery of ancillary services (download here)
    This document provides an overview of the roles and responsibilities as required by the European Guidelines. Concretely the document describes the impact on the contractual and operational frameworks, overview of future milestones and projects, interdependencies between different roles, and references to other useful documentation.
  • Design note for the coordination of assets: Part I – Outage Planning (download here)
    This document describes the modalities regarding outage planning, such as the role and responsibilities of the Outage Planning Agent, asset obligations, exchange of information in terms of content and timing, possibilities to modify outage plans, and remuneration.

  • Design note for the coordination of assets: Part II – Scheduling and Redispatching (download here)
    This document describes the role and responsibilities of the Scheduling Agent and rules on asset obligations (with respect to the delivery of schedules and the bidding of flexibility to be used by ELIA for redispatching), exchange of schedules and possible schedule modifications, congestion bids, remuneration schemes, activation controls, and penalties.

  • Design note for the coordination of assets: Part III – Congestion Risk Indicator (download here)
    The document describes how ELIA determines the congestion risks via a Congestion Risk Indicator and how this indicator will be used for congestion management and the provision of balancing services.

*
*
You will also receive an acknowledgement email when you complete the consultation.
*
*
*
Almost done...

You are about to submit your response. By clicking 'Submit Response' you give us permission to analyze and include your response in our results. After you click Submit, you will no longer be able to go back and change any of your answers.

Answer confidential?


It is important to know that Elia will consolidate the different remarks and publish them on its website at the end of the consultation unless the respondent requests confidentiality in its response. The Elia response to the remarks made will be provided via a consultation report. This consultation report will also be published on the Elia website.
*