Available generation capacity forecast

This page contains an overview of the available generation capacity of facilities with a CIPU contract.

This forecast covers a period extending from one day ahead to the end of the current year for facilities with a CIPU contract (Contract for the Injection of Production Units).

For more information about generation unit publications, please visit the general page Power generation.

Disclaimer: Information about forecasts of the available capacity of the “Langerlo 1”, “Langerlo 2” and “Plate Taille” generating units will not be published on this page from 1 January 2015 onwards. Information about these units is available either on the Transparency Platform or from the producer.

Producers participating to this publication: EDF Luminus, Electrabel, Eneco Energy Trade, Enel Trade, RWE Supply & Trading, T-Power.

Available capacity forecast of all units aggregated by fuel type


 

Click on the link below to view the details of the available generation capacity forecast. This provides an overview of the total installed capacity and the available installed generation capacity per quarter-hour period (in total and by fuel type).

Available generation capacity forecast (XLS)

Available capacity forecast by unit exceeding 100 MW

The table below details the available generation capacity forecast for the units exceeding 100 MW. This provides an overview of the available capacity forecast for 7 days (one value per unit per day). You can request the available capacity forecast per unit for the whole year on the page “Data download”.

Available generation capacity forecast by units (having more than 100MW of installed capacity) 19/11/2017 -> 25/11/2017
Unit 19-11-2017 20-11-2017 21-11-2017 22-11-2017 23-11-2017 24-11-2017 25-11-2017
Amercoeur 1 R GT 289.89 289.90 289.60 289.73 289.68 288.46 289.63
Amercoeur 1 R ST 156.09 156.10 155.94 156.01 155.98 155.33 155.95
Belwind Phase 1 171.00 171.00 171.00 171.00 171.00 171.00 171.00
COO 1 T 144.00 144.00 144.00 144.00 144.00 144.00 144.00
COO 2 T 144.00 144.00 144.00 144.00 144.00 144.00 144.00
COO 3 T 144.00 144.00 144.00 144.00 144.00 144.00 144.00
COO 4 T 0.00 0.00 0.00 0.00 0.00 0.00 0.00
COO 5 T 215.00 215.00 215.00 215.00 215.00 215.00 215.00
COO 6 T 215.00 215.00 215.00 215.00 215.00 215.00 215.00
DOEL 1 443.05 424.00 442.40 442.49 442.86 442.20 442.52
DOEL 2 440.79 435.65 438.91 439.07 439.87 438.60 393.00
DOEL 3 0.00 0.00 0.00 0.00 0.00 0.00 0.00
DOEL 4 1034.62 1035.00 1031.64 1031.95 1033.34 1031.02 1032.02
DROGENBOS GT1 119.00 119.00 119.00 119.00 119.00 119.00 119.00
DROGENBOS GT2 119.00 119.00 119.00 119.00 119.00 119.00 119.00
DROGENBOS ST 0.00 0.00 0.00 0.00 0.00 0.00 0.00
HERDERSBRUG GT1 157.00 157.00 155.64 155.85 156.56 155.34 156.86
HERDERSBRUG GT2 159.31 163.07 155.64 155.85 156.56 155.34 156.86
HERDERSBRUG ST 157.62 157.62 157.62 157.62 157.62 157.62 157.62
Marcinelle Energie (Carsid) 393.00 380.00 380.00 380.00 380.00 380.00 380.00
Nobelwind Offshore Windpark 165.00 165.00 165.00 165.00 165.00 165.00 165.00
Northwind 216.00 216.00 216.00 216.00 216.00 216.00 216.00
RINGVAART STEG 365.00 365.00 365.00 365.00 365.00 365.00 365.00
RODENHUIZE 4 205.00 205.00 205.00 205.00 205.00 205.00 0.00
SAINT-GHISLAIN STEG 0.00 340.00 349.85 351.75 350.27 347.51 350.40
Scheldelaan Exxonmobil 109.31 140.00 140.00 140.00 140.00 140.00 140.00
Thorntonbank - C-Power - Area NE 149.00 149.00 149.00 149.00 149.00 149.00 149.00
Thorntonbank - C-Power - Area SW 0.00 0.00 0.00 0.00 0.00 0.00 0.00
TIHANGE 1N 0.00 0.00 400.00 400.00 400.00 400.00 484.55
TIHANGE 1S 0.00 0.00 400.00 400.00 400.00 400.00 484.55
TIHANGE 2 1020.14 1019.23 1008.81 1012.49 1009.94 1005.85 1008.02
TIHANGE 3 1046.65 1040.00 1039.91 1000.00 1000.00 1000.00 1000.00
T-power Beringen 422.00 422.00 420.00 420.00 420.00 420.00 420.00
Zandvliet Power 345.00 385.10 383.78 384.38 387.46 382.57 384.53
Zelzate 2 Knippegroen 300.00 300.00 314.65 314.72 314.97 314.15 314.75

 

Click on the link below to view the details of the available generation capacity forecast per unit for 7 days.

Available generation capacity forecast by unit