High-voltage substation Sint-Amandsberg

Renewal of the Sint-Amandsberg high-voltage substation.

High-Voltage substation Sint-Amandsberg
  • texteBenefits to society
    To prepare the electricity grid around Ghent for the future, Elia is carrying out work in various high-voltage substations. Elia is installing new electrical installations so that the electricity supply will continue to be guaranteed in the future. 
  • texteWorks

    As part of the Ghent East project, Elia is carrying out the following activities at the high-voltage substation on Dendermondsesteenweg 406 in Sint-Amandsberg:

    • Installation of new switching equipment 

    This is similar to the electricity distribution box in a house, but then on a much larger scale.

    • Replacement of the existing transformer 

    A transformer converts voltage from a higher to lower level and vice versa. A new transformer, with more power, will ensure that Elia can convert more high-voltage electricity (36 kV) into medium-voltage (12 kV). In addition, the transformer will produce less humming noise for the environment.

    • Extension of 36 kV building and new Fluvius building

    The new transformer requires more space, which is why the 36 kV building is being expanded. A new building will also be constructed next to the existing Fluvius building: here the Fluvius switching equipment will be installed.

  • environnementEnvironment

    Elia is always mindful of the local area when carrying out work. The high-voltage system operator takes a range of measures intended to mitigate disruption and impact on the surrounding area.

    • Work will only take place during the day, between 7 a.m. and 7 p.m.
    • If local residents are set to experience a temporary increase in disruption for a specific reason, Elia or its subcontractor(s) will always individually notify those affected.
  • Schedule
    • November/December 2022: submission of permit
    • Early 2023: information market
    • Early 2024: start of Elia work
    • Early 2026: start of Fluvius work
    • End of 2026: end of Elia work
    • End of 2028: end of Fluvius work
  • docDocuments

News



Contact us

If you are affected by a project and want to ask us something, please feel free to contact us.
Our team would be happy to help.

This website uses cookies to provide you with an optimal browsing experience. Some cookies are strictly necessary for the operation of this website and cannot be rejected, while others are used for analytical/functional/targeting purposes and can be rejected. For more information, please consult ourCookie Policy . You can manage/change your cookie preferences at any time. If you do not manage your preferences, only the cookies which are strictly necessary will be accepted.