    25 June 2020

    Resumption of work

    On 15 June, Elia started work to replace the electric wires on the Horta-Avelgem high-voltage line (380 kV). This is taking place in accordance with the measures announced to limit the spread of the coronavirus (COVID-19).
  • 01 September 2019

    Horta-Avelgem: news item

    The photo below captures a highly complex operation in a single image. Along the E17 in Kruisem, electricity wires are being transferred from the smaller temporary pylon (hidden behind the large pylon) to the new permanent pylon (the large structure in the foreground).
  • 01 September 2018

    Elia secures an environmental permit for Horta-Avelgem

    Last week, Elia secured an environmental permit from the Flemish Government for the Horta-Avelgem project.

  • 01 May 2018

    Elia submits permit application

    Elia has submitted a permit application for the Horta-Avelgem project.