Bruges-Sijsele

Installation of new underground electricity cables to supply energy to the Bruges area

New 36 kV double cable connection to replace the existing cable

System operator Elia is planning work in the area around Sijsele so that security of supply will continue to be guaranteed. The project involves laying a new underground 36 kV double cable between Bruges and Sijsele. Sijsele is currently supplied with power by two separate cables from Eeklo and Bruges. The new 36 kV underground cable is a double connection that will replace the two separate cables.

  • texteIn the interest of society
    Elia is planning to lay new 36-kV underground cables between Bruges and Sijsele. The existing cables date from 1937 and have reached the end of their service lives. This project will allow Elia to continue guaranteeing the security of supply in the Bruges area in the future. Once work is complete, the current outdated connection will be decommissioned.
  • texteThe route

    The new 36-kV underground cables will be laid between the existing substations in Bruges and Sijsele. The cable connection is around eight kilometres long and runs along Altebijstraat, Maalse Steenweg (N9), Vossenberg, Rijckeveldestraat and Kerkweg. Thanks to earlier modifications to the grid and by laying two electricity cables at the same time, Elia can replace the existing 31-kilometre-long connection between Bruges and Eeklo with a shorter underground cable.

     



  • environnementEnvironment

    Whenever it is carrying out work, Elia always takes a number of measures to minimise disruption.

    • The work is being performed in nine phases, each involving a section measuring between 500 and 800 metres. This will limit the duration and scale of the impact on the surrounding area.
    • Homes and businesses will remain accessible at all times while work is under way. Should circumstances mean that they are temporarily inaccessible, however, this will be announced in advance.
    • An Elia accessibility advisor will contact businesses to provide further details regarding their accessibility during the work.
    • Site signs on the road will inform road users about the start and end dates of the work and any possible diversions.
    • Letters will be sent to local residents and businesses, informing them about accessibility and any traffic diversions.
    • Elia will regularly email updates about the work. Sign up for the Bruges-Sijsele project's digital newsletter here. 
    • Elia always prioritises the safety of employees and local residents and an uninterrupted electricity supply when it organises its sites.
  • The schedule

    Elia conducted a detailed study of the cable route in spring 2018. At the start of the permit process in June 2018, Elia organised an information session for local residents and businesses along the route. Elia will start laying the new underground electricity cables in March 2020. This work will be performed in nine phases to limit the duration and scale of the impact on the surrounding area. Work is expected to continue until April 2021.

  • docDocuments

News

03 March 2020

Two information sessions organised regarding the start of the work

Elia held information sessions on Tuesday 18 February (in Sijsele) and Wednesday 19 February (in Bruges) to provide local residents and businesses with information about the start of the work

01 June 2019

Elia submits permit application for work on high-voltage cable between Bruges and Sijsele

Elia is set to replace the old HV cable between Bruges and Sijsele with a new double 36-kV underground cable connection.



Contact us

If you are affected by a project and want to ask us something, please feel free to contact us.
Our team would be happy to help.

Please be aware that we use cookies on our website. By continuing to use this website, or by clicking "I accept", you indicate that you have read and agree with our cookie policy. More information about cookiescan be found here.