Drogenbos – Buizingen

Replacing a 150 kV high-voltage line between the Drogenbos and Buizingen substations.

Keeping the national grid reliable

The current 150 kV high-voltage line has reached the end of its service life. To guarantee the reliability of the national grid and keep the general public and the infrastructure safe, we are replacing the line between Drogenbos and Buizingen. Elia is replacing all the high-voltage pylons along the route with equivalent infrastructure that meets the stringent safety standards applicable today.

  • texteIn the interest of society

    The line between Drogenbos and Buizingen needs to be replaced for two reasons:

    • Current cable at end of service life
      The cable currently linking the high-voltage substations in Drogenbos and Buizingen has come to the end of its service life.
    • Grid safety and reliability
      By replacing the cable, we are keeping the electricity grid reliable and safe and ensuring that it is always supplied with power.

  • texteThe route

    The new 2 x 150 kV high-voltage line will follow the same route as the current line between the Drogenbos and Buizingen substations. Although Elia is replacing twenty high-voltage pylons, the height and voltage level (2 x 150 kV) of the pylons will remain the same.


  • environnementEnvironment
    Elia is keeping interested parties informed about the project through letters to local residents and the project website: www.elia.be/drogenbos-buizingen. Directly affected stakeholders will be contacted personally.
  • Schedule

      • June 2017: Project presented to the local authorities for the towns of Drogenbos, Beersel, Sint-Pieters-Leeuw and Halle.
      • 29 November 2017: Project presented to local residents at an information session.
      • December 2017: Declaration of Public Utility and road permit requested.
      • March 2019: Start of the work.
      • Late 2020: End of the work.

      The work will take place in seven distinct stages:  
      Stage 1: Lopping and clearance

      • Lopping and clearance work may be required at some points along the route. This will be done in consultation with the respective land owners and operators.

      Stage 2: Creating site access roads

      • After surveying the area with the respective land owners and/or operators, temporary access roads will be built for the intermittent traffic needed to carry out the work.

      Stage 3: Dismantling the old pylons

      • The conductors will be removed section by section and immediately rewound using pulling and braking machines. The pylons will be dismantled and the foundations will be removed from the ground and taken away by lorry.

      Stage 4: Laying the new foundations

      • The placement and dimensions of the old foundations will be adapted to the dimensions of the new infrastructure so that concrete foundations can be poured for each pylon. The soil removed to create these foundations will be taken away by dump truck. The new infrastructure will be built in the same location as the current line.

      Stage 5: Erecting the new pylons

      • The new pylons will be transported to the site by lorry. They will be brought there in pieces, assembled on site and then erected. Finally, the cables will be pulled from one end to the other so that they can be attached to the metal crossarms.

      Stage 6: Clearing up the site

      • As soon as the project is finished, the temporary access roads will be dismantled and the land will be restored to its original state. All waste from the site will be collected and taken to an accredited waste processing centre. A final survey of the area around the site will then be carried out.

      Stage 7: Fostering biodiversity

      • The pylons’ feet can be specially designed to limit maintenance costs and strengthen the ecological network. This special manner of construction will be determined together with an external partner, Elia’s teams and certain affected parties. As the project progresses, other opportunities to enhance biodiversity may well arise.
  • docDocuments

News

01 September 2019

Drogenbos-Buizingen: update on works

On the high-voltage line between Drogenbos and Buizingen, 11 of the 18 pylons have already been demolished and replaced and the new electric wires have been hung.


Contact us

If you are affected by a project and want to ask us something, please feel free to contact us.
Our team would be happy to help.

Please be aware that we use cookies on our website. By continuing to use this website, or by clicking "I accept", you indicate that you have read and agree with our cookie policy. More information about cookiescan be found here.