Maintenance scheduled for Monday, 21 september, 2020
In order to continuously improve our services, we are planning a maintenance of this website on Monday 21/09/2020 from 9am to 6pm, during which brief interruptions of service could possibly occur. We apologise for any inconvenience this may cause and thank you for your understanding.

Herentals-Heze project

New underground cables between the Herentals high-voltage substation and the Heze high-voltage substation in Geel with an additional connection to the Umicore site in Olen

New underground cables are needed to continue to guarantee a reliable power supply to the region

Elia is planning to lay new 150-kV underground cables in Herentals, Olen and Geel.

  • texteIn the interest of society

    Elia is planning to lay new 150-kV underground cables in Herentals, Olen and Geel, to enable an expansion and restructuring of the electricity grid. This is necessary to prepare the grid for increasing energy demand in the area. The project will allow Elia to continue guaranteeing a reliable electricity supply for businesses and households in the region in the future.

  • texteThe route

    The 150-kV underground cables will be laid between the high-voltage substation in Herentals and the Heze high-voltage substation in Geel. The approximately 11-kilometre route runs through the municipality of Olen and the cities of Herentals and Geel. Elia is also planning an additional cable connection to the Umicore site in Olen from the Herentals high-voltage substation, a total distance of one kilometre. The routes of both underground cables were established in dialogue with the municipal and city authorities concerned. The work will take place in phases.

  • environnementEnvironment
    Elia is always mindful of the local area when carrying out work. The high-voltage system operator takes a range of measures intended to minimise disruption and impact on the surrounding area.
    • Work only takes place during the day, between 7 a.m. and 7 p.m.
    • Elia guarantees that homes and business will remain accessible at all times while the work is under way.
    • If local residents are set to experience a temporary increase in disruption for a specific reason, Elia or its subcontractor(s) will individually notify those affected.
    • If normal traffic has to be diverted, the diversions will be agreed with the road authority and clearly communicated to local residents.
    • Once work is complete, the land is always restored to its original state.
  • Schedule
    • June 2020: Public consultation as part of the environmental permit application
    • February 2021: Start of the work
    • June 2022: End of the work
  • docDocuments

News

03 June 2020

Public consultation for environmental permit begins

Elia has submitted a permit application for the laying of underground cables between the high-voltage substation in Herentals and the Heze high-voltage substation in Geel.

Contact us

If you are affected by a project and want to ask us something, please feel free to contact us.
Our team would be happy to help.

Please be aware that we use cookies on our website. By continuing to use this website, or by clicking "I accept", you indicate that you have read and agree with our cookie policy. More information about cookiescan be found here.