Site report - Lixhe converster station

Construction work on the station building began last April, and the first concrete shells for its side walls have been erected. So far they have reached roughly half their final height.

The building's main concrete envelope will be finished by the end of January 2019. By the end of the year, the four transformers, the station's centrepiece, will arrive by barge as a special delivery.

This website uses cookies to provide you with an optimal browsing experience. Some cookies are strictly necessary for the operation of this website and cannot be rejected, while others are used for analytical/functional/targeting purposes and can be rejected, except for the cookies used to analyse the traffic. For more information, please consult ourCookie Policy . You can manage/change your cookie preferences at any time. If you do not manage your preferences, only the cookies which are strictly necessary will be accepted.