Planning permit obtained and end of the appeal period

Following the submission of its application for a planning permit to the relevant authorities on 3 July 2020, transmission system operator Elia has now obtained the permit. 

 

With the appeal period expired, Elia is creating a schedule for the project. The installation of the 150-kV underground line between Auvelais and Gembloux substations will ensure grid reliability and incorporate renewable energies. This is an important stage in this project, as it marks the completion of the administrative procedure and makes it possible to move on to the construction phase shortly.  

This website uses cookies to provide you with an optimal browsing experience. Some cookies are strictly necessary for the operation of this website and cannot be rejected, while others are used for analytical/functional/targeting purposes and can be rejected. For more information, please consult ourCookie Policy . You can manage/change your cookie preferences at any time. If you do not manage your preferences, only the cookies which are strictly necessary will be accepted.