Baasrode - Sint-Gillis -Dendermonde

Dismantling the 70-kV overhead high-voltage line and laying a 150-kV underground electricity cable 

Dismantling the overhead air line and laying an underground connection Baasrode – Sint-Gillis bij Dendermonde

With the Baasrode – Sint-Gillis bij Dendermonde project, Elia is upgrading the electricity grid between Baasrode and Sint-Gillis-bij-Dendermonde

  • texteBenefits to society

    Elia will dismantle an existing 70-kV high-voltage line between the high-voltage substations in Baasrode (Buggenhout) and Sint-Gillis-bij-Dendermonde (Dendermonde). The high-voltage line is at the end of its service life and is being taken out of service. The electricity wires will be removed over a length of eight kilometres. 

    Elia will then start laying the 150-kV underground electricity cables in 2022. These underground electricity cables connect the high-voltage substation in Sint-Gillis bij Dendermonde with the high-voltage substation Baasrode. These works are needed to prepare the region for the energy transition. In this way, Elia can continue to guarantee energy supply in the future. 

  • texteThe route

    Both the dismantling of the high-voltage line and the laying of the underground electricity cable take place between the ‘Sint-Gillis bij Dendermonde’ and ‘Baasrode’ high-voltage substations. The route runs through the municipalities of Buggenhout, Lebbeke and Dendermonde.  View the interactive map here:   

  • local residentsLocal residents

    Elia has made clear arrangements to minimise the impact of its work on local residents and the surrounding area. These arrangements will be checked regularly by a site supervisor. 

    • Elia will work in phases to limit the duration and scale of the impact on the surrounding area. 
    • Site vehicles will use the shortest, safest and most accessible routes. 
    • Possible diversions will be discussed with the relevant authorities and announced to local residents in advance. 
    • Workers will use wooden frames or cranes when removing the electric wires in order to minimise the impact of the project on the surrounding area and local residents. 
    • Pedestrians and cyclists will be able to pass the worksites safely at all times. 
    • Once work is complete, the worksites will be restored to their original state. 
     
  • Schedule

    The removal of the electricity wires, the dismantling of the high-voltage pylons and the laying of the 150 kV underground cable takes place in three phases:

    • Q1–Q2 2022: Winding and removal of electrical wires, dismantling of high voltage pylons and removal of foundations
    • 2022–2023: Laying of underground electricity cable between Baasrode (Buggenhout) and Sint Gillis-bij-Dendermonde
  • docDocuments

News

02 June 2022

Elia informs local residents about the laying of underground electricity cables

On Thursday 31 March 2022, an information market took place on the laying of underground electricity cables in the municipalities of Dendermonde, Lebbeke and Buggenhout (Baasrode). Some twenty local residents visited the information market.

Baasrode - Sint-Gillis -Dendermonde

22 April 2022

Removal of high-voltage line electrical cables

Starting on Monday 4 April, Elia will be removing the electricity cables from the high-voltage line between high-voltage stations ‘Baasrode’ and ‘Sint-Gillis-Dendermonde’. The high-voltage line has reached the end of its service life and has been taken out of service. During the work, a changed traffic situation will apply for Donaustraat and Denderbellestraat.



Contact us

If you are affected by a project and want to ask us something, please feel free to contact us.
Our team would be happy to help.

This website uses cookies to provide you with an optimal browsing experience. Some cookies are strictly necessary for the operation of this website and cannot be rejected, while others are used for analytical/functional/targeting purposes and can be rejected. For more information, please consult ourCookie Policy . You can manage/change your cookie preferences at any time. If you do not manage your preferences, only the cookies which are strictly necessary will be accepted.