01 August 2025
Laying of underground high-voltage cable begins
On 4 August, we will start laying a new underground 150 kV cable between the Brugge Blauwe Toren and Waggelwater high-voltage substations. This cable will replace the existing 150 kV line, which will be upgraded at a later date. The works will be carried out in phases and will take a year to complete.
-
10 December 2024
Underground high-voltage cable guarantees energy supply around Bruges
In the future, we will dismantle the existing overhead line between Brugge Blauwe Toren and Waggelwater, ready to build a stronger, new high-voltage line (380 kV) in the same location. However, a local 150-kV connection between Blauwe Toren and Waggelwater will continue to be crucial to guarantee the security of local energy supply. This is why we are planning to lay a 150-kV underground cable between Blauwe Toren and Waggelwater.