Start of work on phase 2 

Preparations for work on the second part of the Boucle de l’Est (East Loop) project have begun. Once lopping and clearance has been completed and the access roads to the pylons have been built, several stages planned to meet various technical and environmental constraints will be undertaken.

These stages are as follows:

  • preparing the site: lopping and clearance (when necessary) and building the access roads to the pylons;
  • taking down the conductors (cables);
  • dismantling the pylons and removing their foundations;
  • laying foundations for the new pylons;
  • erecting new pylons;
  • fitting the new conductors;
  • clearing up the site: removing the access roads, restoring the site to its original state and adding finishing touches (e.g. planting).

This website uses cookies to provide you with an optimal browsing experience. Some cookies are strictly necessary for the operation of this website and cannot be rejected, while others are used for analytical/functional/targeting purposes and can be rejected. For more information, please consult ourCookie Policy . You can manage/change your cookie preferences at any time. If you do not manage your preferences, only the cookies which are strictly necessary will be accepted.