Resumption of work on 1 February
In December, we announced that the Boucle de l’Est line would be re-energised so that the grid would be able to cope with the peak electricity transmission we see every winter.
Now that this period is over, the link has been de-energised to allow our teams to continue working on the second part of the section between Bévercé and Bronrôme.
A total of 54 pylons will be replaced in the next phase of the project.