Resumption of work on 1 February

In December, we announced that the Boucle de l’Est line would be re-energised so that the grid would be able to cope with the peak electricity transmission we see every winter. 

Now that this period is over, the link has been de-energised to allow our teams to continue working on the second part of the section between Bévercé and Bronrôme.

A total of 54 pylons will be replaced in the next phase of the project.  

 
This website uses cookies to provide you with an optimal browsing experience. Some cookies are strictly necessary for the operation of this website and cannot be rejected, while others are used for analytical/functional/targeting purposes and can be rejected. For more information, please consult ourCookie Policy . You can manage/change your cookie preferences at any time. If you do not manage your preferences, only the cookies which are strictly necessary will be accepted.