Start of a new phase
From Monday 15 September 2025, Besix Unitec will begin earthworks and the installation of medium-voltage underground cable infrastructure from Rue d’Hanzinne 73 to Rue de l’Astia 16. This work constitutes the third section of the connection. Once the work in this area has been completed, only two phases of the project will remain to be completed.
This project will help to improve the security of the region’s electricity supply.
Appropriate signage with diversions for light vehicles will be put in place for people who do not live on the section under construction. Residents directly affected will be able to access their homes with waiting times dependent on the progress of the works.
Work on this section is expected to last approximately two months, barring unforeseen circumstances. It will be carried out in the following four stages:
Please see the project's interactive map to view the sections concerned in more detail.