Gerpinnes-Hanzinelle
Installation of a 12.6 kV (medium voltage) underground connection between the Gerpinnes and Hanzinelle substations in order to secure the region’s supply.
-
Benefits to society
To secure the region’s supply
In order to ensure the reliability of the electricity grid and the security of supply of the area, Elia, the transmission system operator in Belgium, will install an underground connection with a voltage level of 12.6 kV (medium voltage), over a length of 7.4 km in the municipality of Gerpinnes and the town of Florennes.
-
Interactive map
Interactive map of the site:
-
ScheduleAccording to the provisional schedule, this project will begin in June 2023 and end in December 2024. Above is an interactive map updated with the progress of the project and the potential impacts on mobility.
-
Documents
News
Gerpinnes-Hanzinelle
16 April 2024
There will now be a free shuttle service between Place d’Hanzinne place and Place d’Hanzinelle!
Gerpinnes-Hanzinelle
04 December 2023
Work site information - N975 - new diversion
In view of the deterioration in the existing two-way diversion and to ensure the safety of motorists and other road users, a new diversion has been in place since 1 December 2023, from rue Donveau in Hanzinelle and rue du Sommet in Hanzinne.
Gerpinnes-Hanzinelle
20 October 2023
Increased safety and diverted route
At the request of the town of Florennes, and to ensure motorists’ and other road users’ safety, all traffic passing through the worksite zone outside working hours will now be prohibited; only local residents will continue to have access to their homes.
Contact us
If you are affected by a project and want to ask us something, please feel free to contact us.