News Petrol-Zurenborg

  • 01 September 2019

    Visit to the Singel (R10) directional drilling site

    On Monday, 19 August 2019, the worksite was visited by members of the Impact Management Working Group (WGIM, an advisory body tasked with coordinating certain work projects in the city of Antwerp). In the initial stage of the Petrol-Zurenborg project, Elia, WGIM reached a number of agreements about the work’s implementation and devised various measures to limit disruption.
  • 01 July 2019

    Elia to occupy one lane of Singel (R10) until the end of August

    Elia has been carrying out work alongside Singel (the R10) in Antwerp since March 2019 as part of its project to lay a new high-voltage line between the Petrol and Zurenborg HV substations.
  • 01 February 2019

    Elia organises information session on 13 February 2019

    Starting in late February 2019, Elia will be working in the parking areas along Singel (R10) and Uitbreidingstraat, between Kielsevest and the ‘Memories’ pub.
  • 01 November 2018

    Elia organises information session on 13 November 2018

    On Tuesday, 13 November 2018, Elia is organising an information session to inform local residents and businesses along the cable route about the purpose, works, schedule and impact of the Petrol-Zurenborg project.

  • 01 November 2018

    General information session

    On Tuesday 13 November 2018, Elia, together with UNIZO Provincie Antwerpen and Smart ways to Antwerp, organised an information session on the Petrol-Zurenborg cable project at deSingel International Arts Campus.