Public consultation ends
On 27 March, the public consultation launched as part of the planning permit application for the project to upgrade the existing 2 x 380 kV overhead line between Avelgem and Avelin came to an end. During the 30-day public consultation, any citizen could examine the application at one of the five local authorities affected by the project: Mont de l'Enclus, Celles, Pecq, Estaimpuis and Tournai.
The application has now been passed to the Wallonia Public Service (WPS) Planning Officer for further consideration. According to the provisional schedule, a decision on the application is expected in June or July. Elia will keep you informed via various channels of communication.