News Connecting the Seraing CCGT power plant to the Elia grid 

  • 12 September 2023

    Work continues on Route de Seraing

    The work required to connect the future CCGT power station  in Seraing to the Elia grid is continuing. This Monday our teams will begin to install junction box pit n° 7 (part of the new underground connection)  alongside the road between Neupré and Seraing.

  • 26 July 2023

    Work continues in Seraing

    While work continues on the Route de Seraing / Rotheux, Elia will shortly be starting work on the next section, located in Rue des Nations-Unies in Seraing.

  • 07 July 2023

    Reminder – Comply with construction site signs

    We are aware of the duration of the construction site and its potential impact, and we would like to remind you that strict compliance with safety instructions and the Highway Code is essential to avoid endangering yourself or others.

  • 12 May 2023

    Progress on the reinstatement of the Route du Condroz

    The construction of the first two sections (between the Rimière substation and the Route de Seraing) has been completed and the reinstatement of the Route du Condroz is now underway.

  • 21 April 2023

    Reinstatement of the Route du Condroz

    The construction of the first two sections (between the Rimière substation and the Route de Seraing) has been completed successfully. The reinstatement of the Route du Condroz can now begin.

  • 10 February 2023

    Reminder: closure of Route de Seraing and Route de Rotheux

    As from Monday 13 February 2023 6am, the Route de Seraing / Route de Rotheux will be closed to car traffic.

  • 07 February 2023

    Preparatory work in Seraing: in compliance with environmental legislation

    In order to comply with the obligations arising from the permit issued to Elia and the legislation in force on the conservation of nature, the felling of trees required for the Elia site will take place on 7 and 8 February 2023, outside the bird nesting season

  • 03 February 2023

    Site news: first section installed

    At the end of January 2023, the electrical installations were successfully installed on the first section of the site (between the Rimière substation and junction 8).

  • 13 January 2023

    First section of Route de Seraing to be limited to one-way traffic starting on January 11

    This week, a directional drilling worksite began between the Chêne Madame crossroads and the start of Route de Seraing. The work is scheduled to be completed in early February.

  • Site info: closure of Route de Seraing and Route de Rotheux

    06 January 2023

    Site info: closure of Route de Seraing and Route de Rotheux

    According to the provisional schedule, our teams will work (execution of a directed drilling) between the Chêne Madame crossroads and the start of Route de Seraing, up to number 4 from 09 January 2023 until early February 2023.

    Works will then continue on Route de Seraing and Route de Rotheux as from early February 2023. According to the provisional schedule, the works on this axis will end around mid-August 2023.

  • 14 November 2022

    Update 18/11 - change of dates

    Mobility information: closure of a section of the Route du Condroz.

    Due to an unfavourable weather forecast for this weekend, this operation is pushed back to Sunday 27/11 and Monday 28/11 (same hours). 

  • 18 October 2022

    Start of construction on 7 November, stay informed with the interactive map

    According to the provisional schedule, the project to install a new 220 kV underground connection to link the future Seraing power station the project to install a new 220 kV underground connection to link the future Seraing power station to Elia’s grid will start on 7 November.

  • 22 January 2021

    Launch of the public consultation

    In connection with the project to connect the future combined-cycle gas turbine power plant in Seraing to the Elia grid, a public consultation will be organised, as required by law. The consultation will run from 28 January to 26 February 2021.
  • 22 September 2020

    Advance public information meeting on 22 September 2020

    As part of the project to connect the prospective Seraing combined-cycle gas turbine power plant in Seraing to the Elia grid, an advance public information meeting ahead of the completion of the environmental impact assessment is being organised.
This website uses cookies to provide you with an optimal browsing experience. Some cookies are strictly necessary for the operation of this website and cannot be rejected, while others are used for analytical/functional/targeting purposes and can be rejected. For more information, please consult ourCookie Policy . You can manage/change your cookie preferences at any time. If you do not manage your preferences, only the cookies which are strictly necessary will be accepted.