Schelle-Malderen-Mechelen

Dismantling high-voltage lines, upgrading high-voltage substations and laying an underground cable connection in the Schelle-Malderen-Mechelen area.

Security of supply in the Schelle-Malderen-Mechelen area

From 2017 to 2021, Elia will be working on four sub-projects in the area around Schelle, Malderen and Mechelen: dismantling the 70 kV overhead line between Schelle and Mechelen, upgrading the high-voltage substations in Schelle, Malderen and Tisselt, laying a 150 kV underground cable connection between Malderen and Mechelen, and dismantling the 70 kV overhead line between Malderen and Mechelen. By carrying out this work, Elia is guaranteeing security of supply in the Schelle-Malderen-Mechelen area.

  • texteIn the interest of society

    Work on the high-voltage grid in the Schelle-Malderen-Mechelen area is necessary for three reasons:

    • Two 70 kV lines have reached the end of their service lives

    The 70 kV line between Schelle and Mechelen is almost a century old and the 70 kV line between Malderen and Mechelen dates from 1932.

    • New 150 kV cable to ensure security of supply

    A new 150 kV underground cable connection between Malderen and Mechelen will replace the 70 kV overhead line between Malderen and Mechelen. Since the new cable’s voltage level is higher, it will guarantee security of supply in the future too.

    • Work on the high-voltage substations to make grid upgrades possible

    The high-voltage substations in Schelle, Malderen and Tisselt need to be upgraded to improve electricity transmission in the Mechelen area.

  • texteThe route

    The Schelle-Malderen-Mechelen project crosses nine municipalities: Schelle, Niel, Aartselaar, Rumst, Mechelen, Londerzeel, Willebroek, Puurs and Kapelle-op-den-Bos.

    Each of the four sub-projects has its own route.

    • Dismantling of the 70 kV Schelle-Mechelen overhead line 

    In 2017, the 16-kilometre overhead line through Schelle, Niel, Aartselaar, Rumst and Mechelen was dismantled and a total of 82 pylons were demolished. The line passed through the municipalities of Schelle, Niel, Aartselaar, Rumst and Mechelen.

    • Upgrade of three 70 kV high-voltage substations in Schelle, Malderen and Tisselt

     This work will take place in Schelle, Malderen and Tisselt.

    • Laying of the new 150 kV Malderen-Tisselt-Mechelen cable 

    This new 150 kV underground cable will pass through the municipalities of Londerzeel, Willebroek, Puurs, Kapelle-op-den-Bos and Mechelen. However, the connection will continue to take the form of an overhead line between Leest and Mechelen. Elia is building a transition pylon in Leest to connect the underground cable with the overhead line.

    • Demolition of the 70 kV Malderen-Mechelen overhead line

    This line also passes through Londerzeel, Willebroek, Kapelle-op-den-Bos and Mechelen.

  • environnementEnvironment

    Even as early on as the design and study phase for a project’s route and implementation method, Elia thinks about how the project will affect people, the environment and the local area. With this in mind, a number of nuisance limitation measures have been put in place for the Schelle-Malderen-Mechelen project.

    • Elia is committed to minimising the duration of the work and the amount of space affected (work areas).
    • After work is completed, the land is always restored to its original state on the basis of a survey.
    • Elia only carries out work during the day, so no depots or sites are lit up at night.
    • Elia agrees specific access routes with the municipal authorities and the local police with a view to spreading out and limiting site traffic.
    • If local residents are set to experience a temporary increase in disruption for a specific reason, Elia or its subcontractors always send out individual letters to those affected to notify them.
    • If normal traffic has to be diverted, the diversions are agreed with the road authority (the municipality or the Flemish Region) and clearly communicated to local residents.
    • Elia keeps local residents informed of the project schedule and upcoming phases by publishing a digital newsletter and posting the latest information on its website.
  • Schedule

    Elia has devised a schedule for each of the sub-projects.

    Sub-project 1: dismantling the 70 kV overhead line between Schelle and Mechelen

    • Spring 2017 – March 2019

    Sub-project 2: upgrading three 70 kV high-voltage substations in Schelle, Malderen and Tisselt

    • Spring 2017 – March 2019: upgrade of the Malderen high-voltage substation
    • Mid-2017 – September 2019: upgrade of the Schelle high-voltage substation
    • Mid-2018 – mid-2020: upgrade of the Tisselt high-voltage substation

    Sub-project 3: laying a new 150 kV cable connection between Malderen, Tisselt and Mechelen

    • March 2019 – mid-2020

    Sub-project 4: dismantling the 70 kV overhead line between Malderen and Mechelen

    • Mid-2020 – September 2021

News

01 April 2019

Elia thanks the local residents

Work on the Maldersesteenweg has been completed. Elia thanked the residents for their patience and understanding by offering them an ice cream or waffle.

01 July 2019

Update on the work on the underground cable connection along Maldersesteenweg

Work on laying an underground cable connection along Maldersesteenweg is progressing according to schedule.



Contact us

If you are affected by a project and want to ask us something, please feel free to contact us.
Our team would be happy to help.

Please be aware that we use cookies on our website. By continuing to use this website, or by clicking "I accept", you indicate that you have read and agree with our cookie policy. More information about cookiescan be found here.